Powerlink was to seek a Ministerial designation for the Ross to Strathmore transmission line under the Integrated Planning Act 1997 as there was not enough local gas for electricity generation.
(Full Article)The proposed 'missing link" pipeline will transport coal seam gas (CSG) for various shippers via the South West Queensland Pipeline (SWQP) and the Queensland to South Australia / New South Wales Link Pipeline (QSN Link), the Moomba to Sydney Pipeline (MSP) and the Moomba to Adelaide Pipeline (MAP). The map - shows the AGL investments.
(Full Article)Nextgen reported in the Queensland GEC market one midweek trade took place in the Cal 08s at $10.75 in 25K. Erisk notes that this appears to relate to an oversupply caused by new coal seam methane.
(Full Article)Unserved energy (blackout risks) in the Queensland region had reduced largely due to significant rainfall in the region in January and February 2008 - in the "average" rainfall scenario.
(Full Article)The tables summarise the annual USE (unsupplied energy - meaning ‘blackout risk”) figures for each region, and provide comparisons between the NEMMCO March 08 report and the 1 July update